Executive summary
Co-location is often called the fastest route to clean energy value capture. This report tests that claim. Arenko convened leading utilities, IPPs and generators from the UK and Europe to ask what stops co-located projects getting off the ground, from connection reform and lender appetite to integration and market rules. It sets out their conclusions, with practical actions for developers, owners, lenders and policymakers.
Who was in the room
The roundtable brought together senior people from across the project lifecycle: developers, owners, optimisers, storage specialists and investors.
- Duncan Clark: Director, Sandforth Green
- Hildagarde McCarville: CEO, Anesco
- Sarah Standen: Head of commercial asset optimisation, UK, RWE
- Richard Thwaites: Executive director and head of UK, BW ESS
- William Chilvers: Head of GB services, ElectroRoute
- Josh Murphy: Director, energy storage, Econergy
- Pawel Kordala: Head of investment office, R.Power Renewables
- John Kinsella: ICENI director, Ørsted
- Rupert Newland: CEO, Arenko
- Roger Hollies: CTO, Arenko
- Bridgit Hartland Johnson: Adviser, Arenko
The technology isn’t the limiting factor. The opportunity lies with evolving the regulatory and contractual frameworks so we can make full use of it.
What this report covers
- The investment case: Why a shared grid connection is a start, not a business case.
- Regulation: How Gate 2, connection dates and stranded capex hold projects back.
- Lenders: Why two assets with two business cases make finance harder, and what helps.
- Integration and performance: Where revenue leaks when assets do not work together.
- Actionable steps: Takeaways and actions for developers, owners, lenders and policymakers.
What’s inside
Drawn from a roundtable of senior figures at utilities, IPPs, generators, storage developers and optimisers, including Anesco, RWE, Sandforth Green, BW ESS, ElectroRoute, Econergy, R.Power Renewables and Ørsted. Ten sections cover the investment case, regulation, lenders, curtailment, integration, future-proofing, performance and speed, each with a key takeaway and action points.
If the investment environment in the UK doesn’t recognise hurdle rates, the capex naturally goes elsewhere.
What you will learn
Learn why connection reform may be pushing storage out of projects, what lenders need to see to get comfortable, how integration failures put revenue at risk, and what to settle before committing development spend.
16-27 points
More of the connection used, every month
95th → 30th
Percentile among GB 2-hour batteries
~10 TWh
Curtailed in GB in 2025
The complexity with standalone BESS investment, and more so co-location, is the requirement for data flows to be moving through the system to allow you to take advantage of the revenue opportunities available.